Project Timeline

Updates

Construction on the facilities with firm transportation agreements began in May 2016 and were placed in service in March 2017. In April 2017, Texas Gas filed a request for an extension of time to complete the re - marketing and constructi on of the facilities necessary for the remaining 100 MMBtu per day of uncontracted capacity. FERC granted the extension of time for one year, until and including March 24, 2019 to complete construction of the authorized facilities and make them available for service.

Availability:

There is 100 MM/day of capacity remaining under this project.